PHOTOS SHOWING THE BUILDING OF THE HOUSE

Click on a picture to se a larger copy.

1/11 2015 During this autumn we have added a shelter roof for fire wood to the garage. The wood storage is over full and we intend to cut down another three trees this winter. 1/11 2015 We have realized we have a need for a space for sand and soil and other things. We have laid out concrete tiles to build a surface connected to the parking. We have also extended the area for plants on the right side.

2/2 2014 First day of the year with outdoor temperature above zero and with sun. Yesterday the panels were covered by snow. Today most of it has melted away from the solar cell panels. You can also see that the snow has started to melt on the upper part of the water panels thanks to sun reflexion. Still the sun is to low to have a considerable effect on the solar cell panels on the roof.

15/12 2013 A rainy sunday our sun cell installation was completed. We have now more than 60 sqm of sun cells on the roof and on the wall between the two roof slabs. Each solar cell panel has an effect of 250 W. We hope we will get about 7 000 kWh per year. That will almost cover up for our use of electricity.

3/6 2013 At last the porch over the laundry room door i finished. The garden is thanks to Ulla growing well. The sloop between the terrace and the lawn will soon be covered with green plants.

13/5 2012 Anders made a compost with two compartments. The lids are made of left terrace planks. In botten we have perforated steel sheets on stones.

This is what it looks like after two weeks.

27/4 2012 We have laid a grass lawn, not big but nice to have in the summer.

January 2012 During autumn we have completed the garage interior. We have panelled the walls and built a loft for wood etc. The electrician has installed inset LED-fittings. He has also installed separate measuring apparatus for garage, hot water and heater. You can see our monthly energy account on the previous page.

Just before the frost we (with expert help!) were able to make stone pavement in front of the garage and around the house.

11/7 2011 We have had leisure time the last months, but now planning of the garden has started and we have built a terrace in level with the living room floor.

The protecting roof makes it possible for us to sit outdoors during summer rain. It also gives a good sun shed during the hotest summer days.

27/3 2011 Since a couple of weeks we have lived in the new house. Still some building work has to be done. Unpacking and sorting all those unneccesary things we have collected through the years take time to sort out (anybody who recognizes it?). We love the open plan, the space in the central part of the house and the view over the landscape with the sea. The architect feels very good when the handicraft people, distributors and friends say: "What a fantastic house!".

Even if we do not like a high indoor temperarure it was a bit cold from the beginning. Now, when the house is warmed up emperature is 1 or 2 degrees higher. When sun shines temperature raises with 2 to 3 degrees. Nights have been frosty all the time.

Pictures show library, view from bedroom, balcony, guest room on upper floor and master's bedroom. Trough the window in the bedroom you can see our old house. The glass in the staircase is great. These photos can not make the rooms justice.

20/2 2011 We are going to have a birthday party in the house though we have still to complete painting and strips. On wednesday the glazier will assemble the glass sheets in the staircase and the railings on the second floor.

We are looking forward to get the time to sit in the leather chairs and watch the birds and roe deers through the windows.

19/1 2011 We had to find the water pipe to make an outdoor water tap.

21/1 2011 Peter och Magnus assembled the stair case - a tricky job.

31/12 2010 Winter has been the coldest in 100 years - but beautiful. With its vitriol painted facades the house fits very well into the wooden environment. The red painted windows give a neccesary paint touch.

Indoors is still a mess everywhere before we can move in. Our plans is to move in first part of February.

31/12 2010 Technical equipment takes a lot of space. Beside the big accumulator tank of 750 litres, shall be expansion tanks for accumulator and solar panels. Pressure tank for water from the well and water filters are also to be located in the same room. Installation engeneers are very satisfied with the space in this room.

The accumulator tank will have 180 mm thick insulation.

On the right in the picture you can see the installation shaft which goes down to the ground floor.

18/11 2010 We have started assembly of the kitchen equipment. 18/11 2010 Installation for toilet is being made. Next week we will cover it and finish the surfaces.
9/10 2010 The house looks much better from the outside when roof tiles are in place. South is is waiting for rain gutters. 18/11 2010 During the last month there has been a lot of different work in the house. The outside is more or less completed. At present most work is done to complete the surfaces of the wet rooms. Ove is working with the tiles around the floor drain in the laundry room.

9/10 2010 Thanks to Kaisa and Rolf we have been able to fix the wooden ceiling in the living room. We managed well though the height reaches from more than 3 metres to 4½. It is a good thing we use pre painted boards. No puttying or painting is needed The room looks ready. We will show it when the wall paneling is done.

The last month we have worked all over the place. Both indoors and outdoors. Nothing is totally complete, but the progress is fairly good.

It is difficult to take photos showing the interior at the moment. The photo to the right shows the entrance with clinician tiles on the floor. Ceiling and niches (window and door) are not complete - and of course not the baseboards (skirting-boards).

Tomorrow we will start arranging the roof tiles on the northern roof slope.

29/8 2010 Eastern exterior is finished.  
13/8 2010 In wet areas and entry hall floor is built up to the same level as other floors. On top there will later be clinker tiles.
7/8 2010 We work indoors or outdoors depending on the weather.We can at the moment lay floors on the ground floor. It will be oak parquet layd on 50 mm thick cellular plastic in most rooms. Outdoors we are completing the facades and the roof. 3500 roofing-tiles has to be carried up on the roofs. Kristofer is a good help with heavy work. this is an old fashioned gym called hard work.
22/7 2010 Western gable i complete at last. We had to buy more panel. We could get them 7.5 meter long and 25 mm thick. This meant even the longest boards could be in one pice.. And now we are moving the scaffold to the eastern side so we can complete that gable too. The scaffold structure is easy to lift, but the platforms are heavy to handle for one person.

14/7 2010 We have now started indoor paneling on the first floor.  In the wet rooms we use so called humid boards (gypsum plates covered with glass fiber) as a bedding for tiles.

18/6 2010 The last weeks we have had full activity with electicians, brick layers and carpet layers.

1/6 2010 The chimeny is ready on the first level. We have started paneling the rooms on the top floor.

7/5 2010 No spectacular changes now. Indoor work continous with instalation of electric cables and ventilation equipment. Samuel and Thomas are the electricians.

2/4 2010 Ceiling on first floor almost ready. Wall frames on upper floor done.

2/4 2010 We can now see the shape of the rooms on the upper floor.

9/3 2010 Windows fixed for ground floor. The skilled carpenters Magnus and Peter helped with the big and very heavy widows. Very good result!.

 

 

The living room will be fantastic!

20/2 2010 We have started with hte beams for the upper story and the winter view from the livingroom is as beautiful as during summer.
10/2 2010 With help of professional carpenters the ceiling work has advanced with speed. We are soon ready to get insulation blowed in between the roof beams.
23/1 2010 The cold has delayed building over a month. The view is as beautiful as in summer.
5/12 2009 Rain has delayed work on the house. At the moment we are still doing the insulation and paneling. Rainy days we work on the layer for electric installation inside the diffusion cover.

1/11 2009 We have started paneling. Panel must be applied before we can apply windows.

24/10 2009 Ulla does a very good job with the important insulation.

The diffusion cover must be airtight. All joints are patched together with tape and widow bays are provided with special plastic sheets that can cover the joints there.

27/9 2009 Walls have 5 insulation layers. Insulation takes up a lot of room before it is in place.

8/9 2009 The house is almost rain secured. 17/9 2009 Wind shield gypsum) is up and we have started insulating.

23/8 2009

6/8 2009

28/7 2009
26/7 2009 Kaisa, Rolf, Kristofer och Anders working on the south side roof.
16/7 2009 Kristofer helps with the roof 500 mm high roof beams. They are much heavier than the 300 mm beams for the garage.

25/5 2009 We have made a good part of the inner framework. Walls are double framework with insulation and a unbroken layer of 290 mm insulation between.
24/4 2009
4/4 2009 We have started building the framework for the main house..
29/3 2009 Facade is painted (grey)! Garage is workshop now.

3/2 2009 Garage roof. Roofing tiles can wait a year. 26/2 2009

23/12 2008 The outer framework and the glue-laminated wood beam. 31/12 2008 On new years eve the roof beams are mounted. Masonite beams are really easy to handle.
7/12 At last it was dry enough to nail wall structures. We start with the garage as a working place. 9 mm plywood is used in corners for stabilisation.
1/12 A tent on the main house foundation will be a shelter for sawing and cutting machines. We can also store some timber in it.
19/11 2008 Concreating.

7/11 2008 Reinforcement is made.

5/11 2008  

We have built 3D models of the two houses. Separate models are made for framework.

31/10 2008
15/10 2008 Lots of cellular plastic insulation for the foundation
2/10 2008

1/10 2008 foundation for house and garage have started.

19/9 2008

18/9 2008 We have to build an infiltration for 6 properties.

16/9 2008 Foundation work has started!

cleaning up after the feelling - beautiful view from the site

12/6 sawing.

26/5 2008 well-boring.

17/4 2008

3/4 2008 transported to saw mill.

29/2 2008 timber carried to the road.

Hous work started 27/1 2008 with logging. 60 trees were felled and cut in lengths in 6 hours.